Text extracted via OCR from the original document. May contain errors from the scanning process.
August 2017 Update
Growing Together
Monthly Newsletter for Columbia University’s
Manhattanville in West Harlem Development
C
olumbia’s long-term plan for the old Manhattanville manufacturing area will revitalize the four former industrial
blocks from 125th/129th to 133rd Street between Broadway and 12th Avenue, and three small blocks along the east
side of Broadway from 131st to 134th Street, into an environmentally sustainable and publicly accessible center for
academic and civic life woven into the fabric of the West Harlem community.
Project Scope
The initial phase of development will include the Jerome L. Greene
Science Center, the Lenfest Center for the Arts, a new home for the
Columbia Business School, and the University Forum. Later phases
will emphasize interdisciplinary scholarship, including biomedical
engineering, nanotechnology, systems biology, and urban and
population studies, as well as housing for graduate students and
faculty.
Current Construction Activity
Jerome L. Greene Science Center
Ongoing testing, balancing, and commissioning of mechanical,
electrical, and plumbing systems are nearing completion. Furniture
installations are substantially complete.
north of W129th Street, south of Lenfest, and west of the Jerome L.
Greene Science Center, is nearing completion. Upcoming work will
include completion of remaining pavers, permanent irrigation, and
Woodland Walk.
Phase 1 Emergency Generator Project
Furnish and install emergency generator plant on the roof of the
Studebaker building to provide emergency power to the
Manhattanville campus. Automatic transfer switch commissioning
at the Central Energy Plant/Jerome L. Greene Science Center is
substantially complete. Operations training is ongoing.
Did You Know?
Lenfest Center for the Arts
HVAC system and elevator testing and commissioning underway.
Security and audio/visual systems punch list in progress.
The Forum
Precast panels erection. Roughing for mechanical, electrical and
plumbing in the below-grade and street-level spaces. Masonry walls
installation at the second level.
Phase 2 Foundations
The support of excavation (SOE) contractor is currently performing
the following activities; mass excavation, installation of temporary
tieback anchors along the north wall (beneath the Studebaker
building) and construction of concrete cap beam (on top of existing
slurry wall). The dewatering system is in operation. Foundation
minipiles are currently underway.
Central Energy Plant (CEP)
Third-party inspection of fire alarm devices is completed. Required
FDNY testing of merged fire alarm devices is complete with letter of
approval pending. Boiler testing equipment setup and testing is
ongoing. Training for systems is ongoing. Electrical system
commissioning testing is ongoing.
Small Square
The first phase of Manhattanville’s open space project, which lies
August 2017 Update
Page 1 of 4
The first Family Workshop at the Wallach Art Gallery’s new location in the Lenfest
Center for the Arts took place on July 29. The next Family Workshop, which is free
and open to the public, is scheduled for Saturday, October 7 from 1 p.m. to 3 p.m.
Nearly a dozen families enjoyed the Wallach Art Gallery's July 29 Making Art
Uptown Family Workshop—the first family workshop at the Wallach’s new
location in the Lenfest Center for the Arts. The afternoon featured art making
stations, family gallery conversations, and the opportunity to contribute to
Maren Hassinger's Fight the Power sculpture.
The next Wallach Art Gallery Family Workshop takes place on Saturday,
October 7 from 1 p.m. to 3 p.m. The event is free and open to the public, and
all families are welcome!
(Over)
What to Expect
Although contractors carefully stage construction activities to
minimize disruption to the surrounding community, the nature of
construction work is such that some disruptions will occur. The
community should expect the following in the coming months:
Regular work hours are 7:00am - 6:00pm Monday through Friday
Weekend work may be performed.
Closure of certain traffic lanes, parking lanes, sidewalks and
crosswalks, including:
No standing on West 125th Street between Broadway and
West 129th Street.
There is a no parking zone in effect on the west side of
Broadway from West 125th to 129th Streets.
Broadway sidewalk is open from West 129th to West 130th
Street. The Broadway parking lane is a no parking zone.
West 131st Street between Broadway and 12th Ave is
closed and will remain closed until early 2019.
West 130th Street between Broadway and 12th Ave is a no
standing or parking zone.
West 129th Street between Broadway and West 125th
Street is closed until the end of the year.
Community Amenities and Benefits
To access the Columbia University’s Community Services Website,
please visit: manhattanville.columbia.edu then click “Community”
in the navigation menu.
Minority, Women, and Local Businesses and Workforce
MWL construction workforce delivered 1,341,442 hours worked,
representing 50 percent of the total workforce hours for the
construction of the new Manhattanville campus. 243,108 hours of
that figure were performed by the local workforce.
Jobs and Opportunities
As the project progresses, we expect additional opportunities for
people with a wide range of skills and experience in the coming
years.
We are working with our construction partners Skanska USA/the
Velez Organization (for the Forum) and Lendlease (for Phase 2
foundations/below-grade) to assist those interested in employment
with construction firms currently working at Columbia. For more
information, please visit the Manhattanville Employment
Opportunities page at manhattanville.columbia.edu/jobsopportunities.
Additional Information
This newsletter and our weekly construction updates (which contain
more specific information about construction impacts) will be
available on the web at manhattanville.columbia.edu and at various
locations at the project site and throughout the Manhattanville area.
Please note that construction activities are subject to change based
on field conditions. We appreciate the patience and cooperation of
everyone who is temporarily inconvenienced by these projects.
Should you have questions about construction activity, call the
Columbia Facilities Services Center at (212) 854-2222, 24 hours a
day, 7 days a week, or e-mail projx@columbia.edu. For more project
information, to view upcoming bid opportunities, and to sign-up for
our e-mail updates visit manhattanville.columbia.edu.
Columbia has made a significant commitment to the minority,
women, and local (MWL) construction contracting and workforce
community throughout the course of the project: MWL construction
trade contracting goal of 35 percent and MWL construction trade
workforce goal of 40 percent. Working with construction contractors Neighboring construction projects not related to
and the building trades, Columbia is working to enhance the role
Columbia
MWL firms and workers play in building the new campus. All figures New York City Economic Development Corporation's West
125th Street Streetscape Improvement Project, please contact
represent non-specialty construction services and related materials.
Patrick Jordan at 917-439-4630 or west125@zetlin.com.
Construction Contracting
In the first quarter 2017 (January 1 to March 31), Columbia paid
$22,616,290 to MWL firms, representing 53 percent of total
construction spend. $16,818,617 of that figure was paid to local
companies.
New York City Department of Transportation’s Protective
Coating of the Riverside Drive Viaduct from St. Clair Place to
135th St., please contact Community Liaison Hugh Smith at
917-434-1385 or via e-mail at riversideviaduct@gmail.com
Cumulatively from August 1, 2008, through March 31, 2017,
Columbia paid $170,026,810 to MWL firms, representing 37
percent of total construction spend, excluding the amount paid to
the construction manager. $66,076,242 of that figure was paid to
local companies.
Construction Workforce
In the first quarter 2017 (January 1 to March 31), the MWL
construction workforce delivered 13,197 hours worked, representing
49 percent of the total workforce hours for the construction of the
new Manhattanville campus. 1,744 hours of that figure were
performed by the local workforce.
Cumulatively from August 1, 2008, through March 31, 2017, the
August 2017 Update
Page 2 of 4
(Over)
Community News
Local High School Students Get Hands-On Experience
through Summer Internship Program at Columbia
members of our team. Whatever we’re doing, he’s doing it with us,”
said Sharmela Girjanand, assistant director of client support
services Facilities and Operations IT. “Bryan has done tasks such as
troubleshooting, end-user support, IT onboarding of new employees,
prepping new POS system (cash registers) for deployment, and
writing code, while also being exposed to the inner workings of the
many IT systems that support Facilities and Operations. He has
gained hands-on experience in a very demanding environment and
has become a valuable part of our team.”
The other interns include (with the department they are working in
parentheses): Zvi Fermaglich (Finance), Sophie Johnson (Planning),
Isis Joseph (Design and Compliance), Josue Mendoza (Code
Compliance), Joel Mentor (Manhattanville Development Group), and
Shenia Thompson (Human Resources). All of this summer’s program
interns live in Upper Manhattan.
Participants in the Columbia University Local Community High School Summer
Internship Program. The program provides students with practical work experience
across Facilities and Operations. All interns live in Upper Manhattan.
In early August, preparations were underway for the next universitywide procurement event to support the minority-, women- and localowned (MWL) vendors participating in the CU Grow program. Only
this time, Camri Taylor – an incoming high school senior – was hard
at work prepping the materials for the event.
“I am aware of Columbia University because of my school, but I never
realized how involved and connected the University is,” said Wolfe,
who attends high school at Columbia Secondary School. “This
experience has given me a different perspective, and I see how
rooted they are in the local community.”
Project News
Jerome L. Greene Science Center Wins Best Academic
Research Project Award for 2017 from Leading
Construction Association
Taylor is one of nine high school students working across Columbia
University Facilities and Operations this summer as part of the
Columbia University Local Community High School Summer
Internship Program. The structured, six-week initiative drew more
than 100 applicants from the local community and around the city.
The program provides high school students with practical work
experience before graduation. In addition, each Friday, interns join
together for an inside look at various aspects of university
administration, from event management to operating a dining venue,
along with a tour of facilities at the Morningside, Manhattanville and
Lamont-Doherty campuses. At the program’s conclusion, each
intern will make a presentation related to their role and learnings for
the summer.
“We designed the program so interns could see the theory and
behind the scenes work that then contribute to the actual product,
whether it be constructing a building or hosting an event,” said Terri
Caldes, director of human resources, who is leading the program for
Facilities and Operations. “Columbia’s enthusiasm behind the
program is one more demonstration of the University’s commitment
to the local community.”
Joining Taylor in working with Strategic Communications and
Construction Business Initiatives is Laura Wolfe, an incoming junior.
Wolfe has spent the summer focused on communications work,
assisting the team with a website data migration project, social
media strategy and more.
Members of Columbia University Facilities and Operations’ Manhattanville
Development Group join with Lendlease and other professional service partners to
accept the Best Academic Research Project Award for the Jerome L. Greene Science
Center from the Greater New York Construction User Council.
The Greater New York Construction User Council, a consortium of real
estate owners and users of construction services, recognized the
Jerome L. Greene Science Center with the Best Academic Research
Project Award for 2017. Representatives of the Manhattanville
Development Group at Columbia University Facilities and Operations
and Lendlease, the construction manager for the Greene Science
Center, accepted the award at the organization’s annual Chairman’s
Reception on June 28 in Midtown.
In addition to the GNYCUC Best Academic Research Project Award,
the Jerome L. Greene Science Center previously has been awarded a
2017 Grand Award from the American Council of Engineering
Companies (ACEC), one of 16 national award winners, and two
awards from ACEC-NY: a 2017 Diamond Award in the Building/
Technology Systems category and a 2015 Silver Award in the
In addition to Strategic Communications and Construction Business
Initiatives, other departments in Facilities and Operations mentoring Structural Systems category.
interns this summer include Planning and Capital Project
The largest research building ever constructed by Columbia
Management, Finance and Administration and the Manhattanville
University, the Jerome L. Greene Science Center provides 450,000
Development Group.
square feet of space for the neuroscience researchers of
the Mortimer B. Zuckerman Mind Brain Behavior Institute, along with
“Our intern, Bryan Coca, came to us wanting an actual help desk
several spaces on the ground level open to all including the Wellness
experience, and we have put him to work just like he is one of the
Center, Education Lab, Brain Index and retail spaces.
(Over)
August 2017 Update
Page 3 of 4
Construction Progress Images
Phase 2 foundations site, looking northeast
The Lenfest Center of the Arts (left) and Jerome L. Greene Science
Center (right), with the Small Square in the foreground,
looking northeast
The Forum, looking southwest
Sustainable Partnerships
Aerial view looking northeast
LEED ND
Stage 1
Platinum
Certified Plan
August 2017 Update
Page 4 of 4