FIVE PALMS
PRELIMINARY SCHEDULE
II)
a
V
Task Name
Duration
Start
Finish
Predecessors
I Ju
[,ItAY
5122
1 929
6/5
6/12
6/19
6126
I
7/3
I
7/10 I 7/17
1
-
Procurement
98 days
Wed 841/11
Fri 10114/11
•
2
Design
23 days
Wed 6/1/11
Fri 7/1/11
4144
3
Budgeting
10 days
Mon 7/4111
Fri 7/15/11 2
- 0%
4
Approval
5 days
Mon 7/18/11
Fri 7/22/11 3
•
5
Site lighting
60 days
Mon 7/25/11
Fri 10/14/11 4
6
Coral tiles
40 days
Mon 7/25/11
Fri 9/16/11 4
7
Roof trusses
30 days
Mon 7/25/11
Fri 9/2/11 4
8
Roof tiles
30 days
Mon 7/25/11
Fri 9/2/11 4
9
Exterior doors
25 days
Mon 7/25/11
Fri 8/26/11 4
10
Finish hardware
20 days
Mon 7/25/11
Fri 8/19/11 4
11
Hurricane shutters
25 days
Mon 7/25/11
Fri 8/26/11 4
12
Sun shades
25 days
Mon 7/25/11
Fri 8/26/11 4
13
A/C Systems
40 days
Mon 7/25/11
Fri 9/16/11 4
14
Generator
60 days
Mon 7/25/11
Fri 10/14/11 4
15
Electrical fixtures
60 days
Mon 7/25/11
Fri 10/14/11 4
18
17
Sitework
83 days
Mon 7/25/11 Wed 11118/11
18
Rough Site
3 days
Mon 7/25/11
Wed 7/27/11 4
19
Underground utilities
2 days
Thu 7/28/11
Fri 7/29/11 18
20
Install generator
3 days Mon 10/17/11 Wed 10/19/11 14
21
Site lighting
5 days
Thu 11/10/11 Wed 11/16/11 24
22
Site concrete
10 days
Mon 8/29/11
Fri 9/9/11 29
23
Stonework
20 days
Mon 9/12/11
Fri 10/7/11 22
24
Finish grade
3 days
Mon 1117/11
Wed 11/9/11 37
25
Landscaping
5 days
Thu 11/10/11 Wed 11/16/11 24
26
27
Building
86 days
Mon 811/11 Mon 11/28/11
28
Slab
5 days
_
.
Mon 8/1/11
Fri 8/5/11 19
29
CMU
15 days
Mon 8/8/11
Fri 8/26/1128
30
Roof truss system
5 days
Mon 8/29/11
Fri 9/2/11 29
31
Roof dose in
20 days
Wed 8/31/11
Tue 9/27/11 30FS-3 days
32
Gutter / Downspouts
3 days
Mon 9/26/11
Wed 9/28/11 31FS-2 days
33
Set exterior doors
3 days
Wed 9/28/11
Fri snotil 31
Critical
Baseline
Project Summary
Critical Split
Baseline Split
External Tasks
Project: Five Palms Prelim 01Jun11
Critical Progress
External Milestone
.
Baseline Milestone
Date: Wed 6/1/11
Task
Deadline
Milestone
•
Split
Summary Progress
,
Task Progress
Summary
Iii
.
Page 1
EFTA_R1_02030325
EFTA02690333
FIVE PALMS
PRELIMINARY SCHEDULE
ID
Task Name
Duration
Start
Finish
Predecessors
Julia
1129
Woly
34 i©
Exterior stucco
15 days
I
Mon 10/3/11
Frl 10/21/11 33
5/22
1
I
6/5
6112
6119
1 6/26 I
7/3
1 7/10 I
7117
35
Exterior painting
10 days Mon 10/17/11
Fri 10/28/11 34FS-5 days
36
Hurricane shutters
3 days Mon 10/31/11
Wed 11/2111 35
37
Sunshade
2 days
Thu 11/3/11
Fri 11/4/11 36
38
Interior framing
5 days
Wed 9/28/11
Tue 10/4/11 31
39
Interior plaster
20 days
Wed 10/5/11
Tue 11/1/11 38
40
Flooring
5days
Wed 11/2/11
Tue 11/8/11 39
41
Interior painting
5days
Wed 11/9/11
Tue 11/1511140
42
NC Systems
30 days
Wed 9/28/11
Tue 11/8/11 31
43
Electrical Rough
5 days
Wed 10/5/11
Tue 10/11/11 38
44
Electrical Finish
3 days Wed 11/16/11
Fri 11/18/11 41
45
Punch List
3 days Mon 11/21/11 Wed 11/23/11 44
46
Clean up
2 days
Thu 11/24/11
Fri 11/25/11 45
47
Inspection
1 day Mon 11/28/11 Mon 11/2811146
48
Completion
0 days Mon 11/28/11 lion 11128/1147
Critical
Baseline
Project Summary
Critical Split
External Tasks
Baseline Split
Project: Five Palms Prelim 01Junl 1
Critical Progress
External Milestone
Baseline Milestone
Date: Wed 6/1/11
Task
•
Deadline
Milestone
Split
Summary Progress
Task Progress
Iji
.
Summary
Page 2
EFTA_R1_02030326
EFTA02690334
FIVE PALMS
PRELIMINARY SCHEDULE
August
September
October
November
I December
7/24
7131
8/7
8/14
8/21
8/28
9/4
9/11
9/18 1 9/25
102
10/9
10/16
10/23 1 10130
11/6 1 11/13 J 11f20
11/27 I 12/4
4 0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
4 0%
0%
0%
—
0%
0%
0%
4 0%
0%
0%
0%
►
• ,0%
0%
Project: Five Palms Prelim 01Jun11
Date: Wed 6/1/11
Critical
Baseline
Project Summary
Critical Split
Baseline Split
External Tasks
Critical Progress
Baseline Milestone
External Milestone
Task
Milestone
•
Deadline
Split
Summary Progress
Task Progress
Summary
Iti
m.
Page 3
EFTA_R1_02030327
EFTA02690335
FIVE PALMS
PRELIMINARY SCHEDULE
August
September
7
-
2/111 7/31
8/7
1
8114
1 821 1 8/28
9/4
9/11
9118
1
9/25
October
November
I December
10/2
10/9
10116
I 10/23 j 10/30
11/6 I 11113
J 11f20
11/27 I 12/4 I
0%
0%
0%
0%
0%
0%
‘11/28
Project: Frie Palms Prelim 01 Junl 1
Date: Wed 6/1111
Critical
Baseline
Project Summary
Critical Split
Baseline Split
External Tasks
Critical Progress
Baseline Milestone
External Milestone
Task
Milestone
•
Deadline
Split
Summary Progress
Task Progress
Summary
Iji
.
Page 4
EFTA_R1_02030328
EFTA02690336
Technical Artifacts (5)
View in Artifacts BrowserEmail addresses, URLs, phone numbers, and other technical indicators extracted from this document.
Phone
2690333Phone
2690334Phone
2690335Phone
2690336Phone
2811146Forum Discussions
This document was digitized, indexed, and cross-referenced with 1,400+ persons in the Epstein files. 100% free, ad-free, and independent.
Annotations powered by Hypothesis. Select any text on this page to annotate or highlight it.